Pardon Our Dust...

Belt Line Road Overlay


PROJECT UPDATES

Friday, August 1 Update

The Belt Line Overlay project will be completed this week. Staff is currently working with the contractor to schedule a final walk-through of the project to develop the punch-list. 

The Belt Line Underground Electrical project will also be completed this month. The contractor is finishing the final few sections of concrete sidewalk and all work should be completed by mid-August. Staff will work with the contractor to schedule a final walk-through of the project to develop a punch-list once they are complete.

Friday, July 20 Update

Hopefully, you've noticed the progress on the Belt Line Road Overlay project. The asphalt work, which is taking place at night to minimize the impact on traffic, is beginning to wrap up. The entire project is on schedule to be completed by the end of July. 

Friday, June 25 Update

TexBit, Addison’s contractor for the Belt Line Road Overlay project, is planning to start laying down asphalt on Sunday, July 1, weather permitting.  They will begin at Marsh Lane and head eastbound, starting with the inside lanes.  No work will take place on July 3 or July 4.  

 

Friday, June 8 Update

The Belt Line Road Overlay Project continues to make progress. TexasBit, the Town’s contractor for the project, has started sealing the concrete joints. The purpose of sealing joints is to minimize infiltration of surface materials, such as water and dirt, to prolong pavement life by providing protection to the concrete subgrade. TexasBit is also making repairs to the concrete street, curb ramps, and sidewalks. Once complete, they will begin to place the new asphalt and pavement markings. We anticipate the asphalt replacement starting at the end of June. The project is currently on schedule and we anticipate completion in July.

 

Friday, April 27 Update

Addison's contractor TexasBit has completed the milling portion of the Belt Line Road Overlay project on time.  Town staff will have concrete subgrade inspections completed by early next week so TexasBit can begin making any needed concrete repairs.  After that is complete, TexasBit will begin to place new asphalt, which is slated to begin at the end of June. The project is currently on schedule and we anticipate completion in July.

 

Friday, April 14 Update

The Belt Line Road Overlay milling portion of the project will begin at 7pm on Sunday, April 15. Milling operations will start at the westernmost intersection of Belt Line Road and Marsh Lane, then proceed east to the Dallas North Tollway. All the existing asphalt will be removed so the Town officials can inspect the concrete subgrade. Concrete repairs will be made and the asphalt and pavement markings will then be replaced. TexasBit, the Town's contractor, anticipates the milling effort to take three weeks, depending on weather conditions and other factors. 

 


PROJECT OVERVIEW

The 2012 Bond Program included a project to underground the overhead utilities on Belt Line Road from Marsh Lane to the Dallas North Tollway. Phase 1 of this project, from Marsh Lane to Midway Road, is nearing completion.  In March 2017, the Addison City Council made the decision to delay Phase 2 of the utility undergrounding project to underground the utilities from Midway Road to the Dallas North Tollway.  However, in addition to directing staff to move forward on a Phase 1.5 designed to beautify Phase 1, Council gave direction to move forward with an overlay of Belt Line Road from Marsh Lane to the Tollway.  You can view that meeting here.

 

An “overlay” is a street maintenance technique that requires the removal of the top layer (2 inches) of a street by the grinding action of a large milling machine. After the top layer is removed, a new layer of pavement is put in its place. Once the new asphalt is complete, pavement markings will be installed.

 

At the February 27 City Council Meeting, the Addison City Council approved a $2.2 million contract for the work which will begin in mid-March and take four months.  Portions of the project work will be completed between the hours of 9:30am to 3:30pm for the installation of ADA compliant curb ramps and concrete work while the remaining overlay will be performed from 7:30pm to 6:30am to minimize the traffic impact on the community.

If you would like to speak with a Town representative regarding the Belt Line Road Overlay Project please contact Todd Weinheimer, the Streets and Stormwater Manager, at 972.450.2841 or email him at tweinheimer@addisontx.gov.

 

SIGN UP FOR ALERTS!

 

TEXT ALERTS

Opt-in by texting the word “BeltLine” to 888-777 (no space between "Belt" and "Line", keyword is not case sensitive) 

EMAIL UPDATES

Register at bit.ly/BLRUpdates (link IS case sensitive)   