Kellway Lift Station Bypass Improvements

Project Type:
Capital Project
Sewer
Utilities
Project Status: 
Complete
Location: 
Kellway Lift Station
Kellway Lift Station

The project scope consists of installing a new third pump, valving, piping, a new manhole, adjustments to the wet well, a new wall core, and appurtenances. The changes to the wet well will allow the Town to inspect, drain, and perform maintenance on the wet well. The new third pump will optimize the operational efficiency and effectiveness of the current pumping system.

Status Updates

August 2022:

The project is now substantially complete. Town staff has completed a project walkthrough of the project to identify any punch list items that are outstanding.

July 2022:

Project completion has been delayed due to the long lead time of pump and motor items. The contractor is working on the completion of electrical work and instrumentation controls until the items arrive.

January 3, 2022:

The contractor has begun work at Kellway Lift Station. The contractor is working on excavating for the installation of pipes.

September 27, 2021:

Construction is anticipated to begin in December. 

May 25, 2021

City Council approved a construction contract with Rey-Mar Construction.

July 24, 2020:

The Town has executed an agreement with Garver, LLC. for the design of the Kellway Liftstation Bypass Improvements Project.