Proposition B - North/South Roads (Quorum Drive/Montfort Drive)
The sale of $33,602,000 in general obligation bonds for street improvements.
Reconstruction of Quorum Drive from Dallas North Tollway to DART rail right-of-way
Estimated Cost: $26,302,000
- Built in 1980 and 1985
- Asset Management Risk Score based on Addison’s Asset Management Plan: Red
- Current Pavement Condition Index based on Addison’s Pavement Condition Index: Fair
- Rebuild concrete roadway
- Upsize existing utilities
- Install Master Transportation Plan elements including:
- South of Belt Line, sidewalks will be 8-foot wide with a 6-foot parkway buffer
- North of Belt Line, sidewalks will be 15 foot back of curb
- Acquire right-of-way for medians, sidewalks, and landscaping
- Replace 3 traffic signals
Reconstruction of Montfort Drive from Belt Line Road to the Addison city limits
Estimated Costs: $7,300,000
- Built in 1981
- Asset Management Risk Score based on Addison’s Asset Management Plan: Red
- Current Pavement Condition Index based on Addison’s Pavement Condition Index: Very Poor
- Rebuild concrete roadway
- Upsize existing utilities
- Install Master Transportation Plan elements including:
- Widening the median
- Almost doubling the sidewalk width to 8 feet
- Adding a 6-foot parkway buffer.
- Acquire right-of-way for medians, sidewalks, and landscaping
Project scope, locations, and cost estimates are based on information currently available and are, therefore, subject to change on the basis of new and refined information up to the time of completion.