Keller Springs Reconstruction

Project Type:
ADA
Bond / CO Project
Drainage Improvements
Sewer
Streets / Sidewalks
Utilities
Project Status: 
Under Construction
Location: 
Keller Springs Road

Proposition A of the 2019 Bond Program is the reconstruction of Keller Springs Road from the Dallas North Tollway to Addison Road.  Keller Springs was originally built in the late 1970s with asphalt and will be reconstructed with concrete. The utilities will be upsized to handle continued growth in Addison, the Master Transportation elements will be installed, and the traffic lights at the Quorum Drive intersection will be replaced.


Ways to Stay Informed

  • Subscribe to Email Updates
  • Register for text Updates by texting the word KellerSpring to 888-777
  • Follow @TownofAddison on Facebook and Twitter

Get a Bird's Eye View

 

Status Updates

March 2024:

Oncor has begun moving electrical lines to the newly installed electrical poles. Project staff is coordinating with AT&T and Atmos to begin working on adjusting their infrastructure prior to the Town's contractor mobilizing to begin work on the reconstruction project.

January 2024:

Oncor Electric has mobilized and began making adjustments to prevent conflicts once major construction activities begin. Telecommunication utilities will also begin to mobilize to adjust their infrastructure as well.

September, 2023:

The contract was awarded to Tiseo Paving Company during the September 12th City Council meeting. Work is expected to commence in January.

July 2023:

Proposals for the Keller Springs Road Utility, Storm, and Pavement Improvements Project were re-advertised in May 2023. Proposals were closed on June 29, 2023. Staff is evaluating the proposals.

January 2023:

On October 12, 2022, staff issued a Request for Proposals on CIVCAST as Solicitation #22-72 for the Keller Springs Road Revitalization Project. Proposal responses from two construction companies were opened on November 17, 2022.

The two proposals that were received were over the project budget. Town staff and the design engineer will work together to implement ways to reduce the project cost and make the proposals more competitive. 

Staff intends to re-issue the Request for Proposals once the project's scope and design changes are finalized. City Council formally rejected the bids on January 24, 2023.

October 2022:

The construction phase for the project is out for bid.

January 31, 2022

The design is 100% complete. Right-of-Way acquisition is still in ongoing negotiations.

July 27, 2021

The design is 95% complete. The Town is preparing preliminary right-of-way documents and appraisals for acquisition. 

March 9, 2021

The design is 65% complete. Bidding for construction is scheduled for the late summer of 2021.

August 31, 2020

The 30% conceptual design is complete. The 65% design is estimated to be completed in March of 2021.

December 10, 2019

Council has approved the design contract to Jacobs Engineering.