Vitruvian West 3 Streetscape Improvements - Phase 5, Block 200C Vitruvian Public Infrastructure

Project Type:
Bond / CO Project
Project Status: 
Complete
Project Exhibit

Vitruvian West 3 Streetscape Improvements in the Vitruvian Phase 5, Block 200C, is located along Westgate Lane and Marsh Lane. The scope of work for the project will include demolition of existing pavement, construction of new streetscape enhanced sidewalks, pavers, landscape, irrigation system, and electrical improvements necessary to serve the Vitruvian West 3 private development.

Status Updates

February 2023:

Awaiting the project closeout documentation from the contractor.

January 12, 2023:

The final walk-through inspection was conducted. The project has been completed and accepted.

December 2022:

Construction is near completion. A preliminary walk-through inspection was conducted on November 20th. The contractor fixed deficiency punch list items on the project, and the Town staff and team conducted the prefinal walk-through inspection.

August 9, 2022:

City Council awarded the construction contract to Groves Electrical Services.

May 2022:

The project was advertised on CIVCAST for bids.

July 9, 2019:

City Council authorized a Professional Services Agreement (PSA) with Icon Consulting Engineers (Icon) for design services associated with Vitruvian West 3 Streetscape Improvements in the Vitruvian Phase 5, Block 200C. The design for this project was completed in April 2022.

May 3, 2022:

The project was advertised on CIVCAST, and the advertisements were closed on May 31, 2022. The Town received only one bid proposal.

Files:
PDF icon Plans (12 MB)
PDF icon Addendum #1 (52 KB)