Update on DWU's White Rock Creek Restoration Work

Published:
Mon 5/9/22
<< Back to News
temporary fencing along trail

Addison Staff recently received an estimated timeline from Dallas Water Utilities for the restoration of White Rock Creek associated with their water line repair.

 Survey and geotechnical field work – Complete within the next 2 weeks

  • Sod and turf restoration from repair after survey and geotechnical field work – Complete by end of May 2022 (pending verification of vendor availability and operations schedule)
  • Design Complete – June 2022
  • Construction Start – July 2022
  • Construction Completion – September 2022

 The timeline is subject to change but DWU believes it is a good estimation. They have recently added temporary netting to discourage trail goers from cutting through the residential area from the trail.

Addison Public Works and Engineering Services staff will continue to monitor the situation and provide assistance if needed. If you have additional questions, please contact DWU Water Distribution Manager Ryan Corbello at 214-766-7643 or by email at ryan.corbello@dallascityhall.com. You can also contact the Town's Senior Construction Inspector Phillip Willis at 972-450-2847 or by email at pwillis@addisontx.gov