Council Approves Contract with Kimley-Horn and Associates for Montfort Road Revitalization Project

Published:
Mon 5/1/23
<< Back to News
Montfort Drive Reconstruction map

Voters approved the reconstruction of Montfort Drive from Belt Line to the southern town limits as part of Proposition B in the 2019 bond election. Originally scheduled to begin after Quorum Drive was completed in mid 2027, the $7.3 million Montfort Drive Revitalization Project is now anticipated to begin in 2024. At its April 25 meeting, the City Council approved a contract with Kimley-Horn and Associates for professional engineering services that includes surveying, Right-of-Way and easement acquisition services, a traffic signal warrant study, and project design.

The project, which will take 12 months to design and 12 months to construct, includes replacing all existing pavement, upgrading all Town-owned water and sewer lines, and installing new sidewalks and landscaping.

You can watch Council's discussion here and read the presentation here.