Main Lane Demolition of Midway Road from Keller Springs to Dooley to Begin the Week of February 27

Published:
Mon 2/27/23
<< Back to News

Main lane pavement demolition in the northern segment of the Midway Road Revitalization Project will begin the week of February 27. The southbound lanes from Keller Springs Road to Dooley Road will be closed and all traffic will be moved to the northbound lanes. The traffic configuration will have one lane of traffic in each direction and a continuous left turn lane in the center. Drivers should pay close attention to the traffic control and lane assignments in this area and observe the location of signal heads and directional signage at the intersections.

The lime stabilization process of the main lane subgrade of Midway Road from Belt Line Road to Proton Drive is underway. After a “cooking period” the lime subgrade will be remixed and then compacted into its final configuration. Next will be the installation of the reinforcing steel and joints and finally the placement of the street Pavement.

 You can register for Midway Road text updates by texting the word Midway to 888-777 or subscribe to email updates at www.Addisontexas.net/midway. Thank you for your patience as we strive to make Addison a better place to live, work, and play.