Midway Road Revitalization Phasing Revised

Published:
Mon 5/2/22
<< Back to News

Work on the Midway Road Revitalization Project kicked off in March 2021. Over the last year, Addison has made significant progress. The video above provides a behind-the-scenes look at the work currently underway.

 

The construction team anticipates having the majority of the construction south of Belt Line Road completed by the end of 2022. The phasing for this part of the project has recently been revised to help minimize the impact on the public. The northbound lanes from Spring Valley Road to Proton Road are currently under construction. Crews will then move to the southbound lanes between Spring Valley and Proton. Once the southernmost part of the project is completed, they will move back to the northbound lanes from Proton to Belt Line and finish this segment of the project with the southbound lanes from Belt Line to Proton. The contractor anticipates spending roughly 90 days in each section.

 

This revision will allow for the reconstruction of the intersection at Hornet Road to be completed while Greenhill School is out for the summer and minimize the amount of construction adjacent to Belt Line Road during Kaboom Town!  

 

You can register for Midway Road text updates by texting the word Midway to 888-777 or subscribe to email updates at www.Addisontexas.net/midway. Thank you for your patience as we strive to make Addison a better place to live, work, and play.