Midway Road Revitalization Project Update

Published:
Tue 5/30/23
<< Back to News
Paving Operation

The Midway Road Revitalization Project is making steady progress along the corridor. Recently, the west side of the northern section of Midway Road, from Keller Springs Road to just north of the Dooley/Boyington intersection, underwent main lane paving. The work in the northern section will continue with demolition, soil stabilization, and paving toward Lindbergh Drive. In the southern section, the contractor will focus on the east side of Midway Road, working northward from Belt Line Road to Proton Drive.

Efforts to adjust franchised and private utilities, and construct sidewalks, trails, and accessible ramps are ongoing on the west side of Midway, from Spring Valley Road to Belt Line. Additionally, new traffic signals are being installed at various intersections along the corridor, and street lighting is being installed throughout.

To facilitate the installation of a new 16" waterline, preparations are being made for boring beneath the DART right-of-way. This process involves navigating utilities, bridges, and other improvements in the area. Boring activities are scheduled to commence in a couple of weeks and are expected to take around three weeks to complete.

Drivers are advised to be attentive to traffic control measures, lane assignments, signal heads, and directional signage at intersections. 

You can register for Midway Road text updates by texting the word Midway to 888-777 or subscribe to email updates at www.Addisontexas.net/midway. Thank you for your patience as we strive to make Addison a better place to live, work, and play.