Paving Underway on Midway from Belt Line to Proton

Published:
Mon 6/26/23
<< Back to News
road paving operation

The Midway Road Revitalization project is making significant progress. Paving on the eastern two lanes of Midway from Belt Line Road to Proton Drive is wrapping up this week. Paving of the third lane is anticipated to begin late next week, weather permitting. Once the roadway is completed, work will refocus on sidewalks, medians, lights, and other amenities.

Construction is also under way at the northern end of the project, where there has been a great deal of paving progress from Dooley Road to Keller Springs Road.