Rawhide Creek Drainage Project Update

Published:
Mon 5/22/23
<< Back to News
residential street paving operation

The contractor on the Rawhide Creek Basin Drainage and ADA Improvements is making remarkable progress on the project. All storm sewer pipes have been successfully installed, and the restoration of the street pavement is swiftly underway. We anticipate finishing the entire street pavement within the next two weeks. Once this milestone is achieved, the contractor will install the storm trap system adjacent to Marsh Lane and commence landscaping and restoration efforts.

Those required to have driveway work performed adjacent to ADA improvements will be contacted directly by staff to coordinate this work. 

Many thanks to the residents for their patience during the project as we work to make Addison an even better place to live, work, and play.