Section of Beltway Drive Screening Wall to be Removed for Utility Work

Published:
Mon 10/31/22
<< Back to News

InTown Homes will remove a 60-foot section of the Beltway Drive screening wall on Monday, November 7 in order to facilitate the extension of a required water line and to install the emergency access driveway and retractable bollards at the restricted access connection between Beltway Drive and Magnolia Street in the Addison Grove development.

Work will commence on November 7 and is projected to be completed by InTown Homes on December 13. Key project milestones include:

  • Removal of a 60-foot segment of the screening wall (Monday, November 7).
  • Potholing of Beltway to locate existing utilities and boring of Beltway for new water line connection (Tuesday, November 8 – Friday, November 11).
  • Install water line connection, chlorinate, pressure test, and backfill trench (Monday, November 14 – Monday, November 21).
  • Install and inspect retractable bollards (Monday, November 28 – Monday, December 5).
  • Test subgrade and install permanent pavement (Tuesday, December 6 – Thursday, December 8).
  • Remove pavement forms and repair landscape (Friday, December 9 – Tuesday, December 13).

While work is ongoing, a temporary chain link construction fence will be utilized to provide required access to the construction site. Solutions for a more permanent construction debris barrier will be identified and installed following completion of the work.

The contractor will stage project-related vehicles, equipment, and materials north of the screening wall and limit construction impacts on Beltway Drive as much as possible. If there are any issues with the work, please contact the Director of Development Services Ken Schmidt at kschmidt@addisontx.gov or 972-450-7027.