Visible Progress on Midway Road Revitalization Project

Published:
Wed 3/22/23
<< Back to News
paving operation

Since Friday of last week, Addison's Midway Road contractor has placed well over 3,500 cubic yards of concrete. The southbound center and outside lanes are complete from Belt Line Road to Proton Drive except for a few driveway leave outs and half of the Beltway Drive intersection. The inside lane is anticipated to be completed by the end of this week depending on weather. All southbound main lane paving south of Belt Line should be completed in the next two weeks.  

Pavement demolition of the southbound lanes from Keller Springs Road to Dooley Road is complete and haul-off operations are underway. The next step is to fine grade the subgrade and lime stabilization which should begin in the next week.

You can register for Midway Road text updates by texting the word Midway to 888-777 or subscribe to email updates at www.Addisontexas.net/midway. Thank you for your patience as we strive to make Addison a better place to live, work, and play.